Pakistan airport outsourcing took a concrete step on Thursday, 19 November. The Privatisation Commission signed a financial advisory services agreement with a consortium led by Ernst & Young (EY) Middle East to prepare the handover of operations at Karachi’s Jinnah International Airport and Lahore’s Allama Iqbal International Airport to private operators. A day earlier, the Public Private Partnership Authority board cleared two sections of the Hyderabad-Sukkur Motorway (M-6) to be built and run by private investors. For business, the two decisions point the same way: the state is asking private capital to fund and run transport assets it can no longer pay for on its own.

The short version

  • The Privatisation Commission signed an advisory agreement with an EY Middle East-led consortium for outsourcing Karachi and Lahore airports.
  • Each airport is expected to attract more than $500m of fresh investment, Privatisation Adviser Muhammad Ali has said.
  • Two M-6 motorway sections will go to private investors on 25-year toll concessions, with state support for Section I only.
  • Neither deal has a bid or award date yet; the advisory work on the airports was expected to take about a year.

What happened

The agreement was signed in Islamabad in the presence of Muhammad Ali, Adviser to the Prime Minister on Privatisation and chairman of the commission, Dawn reported. The commission said the transaction aims to bring private-sector expertise into the operation, management, commercial development and optimisation of both airports through a concession or management contract. The consortium will provide technical, financial, legal, environmental and commercial advice. The commission called the signing “an important milestone” in the privatisation programme. The fee was not disclosed.

The process has been slow. The government decided in December 2022 to outsource the Karachi, Lahore and Islamabad airports. In January 2026 it dropped a government-to-government approach in favour of open bidding, citing investor interest from the UAE, Türkiye and Saudi Arabia. In August, the commission named the EY-Parthenon-led consortium as the top-ranked adviser. Islamabad is on a separate track, with the Asian Development Bank as adviser and a target of issuing its request for proposals by the end of December, as Knock-On reported in its look at Pakistan’s privatisation target for this fiscal year.

Why it matters

Pakistan airport outsourcing is less about sale proceeds than about investment. Mr Ali told Dawn in July that Karachi and Lahore were each expected to draw more than $500m in fresh investment. Taken together, that is more than the government hopes to raise from all state asset sales this fiscal year. The two figures measure different things, but the comparison shows why the airport deals carry weight for the wider economy.

Expected airport investment tops this year’s entire sale target

US$ millions; airport figures are expected fresh investment, target is FY27 privatisation proceeds (top of range)

Karachi + Lahore airports, combined
$1,000m+
FY27 privatisation target, all transactions
$723m
Jinnah International, Karachi
$500m+
Allama Iqbal International, Lahore
$500m+
Source: Dawn (15 Jul 2026, citing Privatisation Adviser Muhammad Ali); Arab News (7 Nov 2026). Combined figure is a Knock-On calculation.

The M-6 decision follows the same logic. Under the approved model, private investors will develop and operate each section for 25 years, recover their money through tolls, then hand the road back to the National Highway Authority. The government will provide viability gap funding for Section I only, to keep tolls affordable. The Asian Development Bank is advising the NHA, which will now invite bids from local and foreign investors.

The M-6 would halve the Hyderabad-Sukkur trip

Approximate journey time, hours

Today, on the N-5 National Highway
About 6 hours
On the completed 306km M-6 (expected)
About 3 hours
Source: Dawn, 19 Nov 2026. The M-6 is planned as five sections; the full time saving needs all of them built.

The knock-on effects

First order: Pakistan airport outsourcing enters the advisory phase

The advisers will now prepare the transaction: valuing the airports, setting the concession terms and marketing them to operators. Nothing changes for passengers yet. The key early signals will be the length of the concession, how revenue is shared with the state, and whether staff and tariffs are protected in the contract.

Second order: terminals, retail and cargo

Private airport operators usually earn much of their money from shops, food, parking and cargo, not only from landing fees. The Prime Minister’s Office said in October that work is under way on an air cargo village to make Karachi a cargo hub, and the runway expansion at Jinnah International has been completed. A private operator with more than $500m to spend would likely build on that, which matters to exporters of perishable goods and to the airlines, including a PIA under new management, that use these airports.

Third order: less pressure on the development budget

Every airport terminal or motorway section financed privately is one the federal development budget does not have to fund. That budget is already stretched: PSDP foreign-funded projects get less than half the rupee cover they need. The trade-off is that users pay more directly, through tolls and airport charges, and the state gives up long-term income.

Who could benefit

  • Construction and engineering firms: terminal upgrades and two motorway concessions open to local and foreign bidders.
  • Retail, food and logistics operators: private airport managers typically expand commercial space and cargo handling.
  • Freight firms in Sindh: a faster Hyderabad-Sukkur link would cut trip times on the north-south corridor.
  • Advisers, lenders and insurers: project finance for 25-year toll roads and airport concessions.

Who may face pressure

  • Road users and hauliers: M-6 costs will be recovered through tolls.
  • Airlines and passengers: private operators may seek higher airport charges to fund investment.
  • Existing airport staff and contractors: new managers usually restructure services.

What to watch

  • End-December 2026: target for the Islamabad airport request for proposals.
  • The NHA’s invitation for bids on M-6 Sections I and II, and the size of the viability gap funding.
  • The advisers’ concession structure for Karachi and Lahore: term, revenue share and investment commitments.
  • Whether investors from the UAE, Türkiye and Saudi Arabia, named when bidding was opened up, take part.

Sources

This is analysis, not investment advice. Figures are as of 19 November 2026.

Share this story

On your phone, tap Share to Story and choose Instagram or Facebook to post this story to your Story. Copy link copies the article address; on some devices it opens your share menu, where you tap Copy.

Spotted an error? Email corrections@knockonbrief.com with the article link. Have a tip? Write to tips@knockonbrief.com. See our Corrections Policy.

Leave a Reply

More from Knock-On

Discover more from Knock-On

Subscribe now to keep reading and get access to the full archive.

Continue reading