The MGM Dubai opening is now set for early 2029, after Wasl announced on 16 November that the structure of the three-hotel resort on a man-made island next to the Burj Al Arab has topped out. The new date is later than the targets MGM Resorts gave earlier, and it arrives as building costs in Dubai rise sharply. For hotel operators, suppliers, contractors and recruiters in the UAE, it sets the timetable for 1,500 new keys, 40 restaurants and a large entertainment venue on the Jumeirah coast.

The short version

  • MGM Dubai, built by Wasl with MGM Resorts, is scheduled to open in early 2029 in a single phase.
  • The 3m sq ft island will hold MGM, Bellagio and Aria hotels with 1,500 keys combined, plus 40 dining venues, a beach club and a theatre.
  • Wasl’s chief executive put the project at about 68% complete and about AED 10bn in cost, according to EnterpriseAM citing Al Bayan.
  • Neither company gave a reason for the later date. Dubai construction costs rose 11.64% in a year to July.

What happened

Wasl said the structure of MGM Dubai had topped out, and the partners said the resort is on track to open in early 2029, Khaleej Times and Gulf News reported. The island sits off the Umm Suqeim and Jumeirah coastline and will be MGM’s first property in the Middle East. China State Construction Engineering Corporation is the contractor. Mustafa Al Hashimi, chief executive of Wasl Hospitality and Leisure, told Khaleej Times the partners intend to open it in one phase rather than in stages. Ari Kastrati of MGM Resorts said about 90% of the theatre’s programming had already been selected.

The date has moved before. According to EnterpriseAM, MGM moved the opening from the third quarter of 2027 to the second half of 2028 in July 2025, and in February this year said construction remained on schedule. Early 2029 is therefore the second change in about 16 months. The cost estimates also differ: MGM’s chief executive said in March the project would “probably cost more than $2 billion” (Gulf News), while Wasl’s chief executive, Hesham Al Qassim, put it at about AED 10bn, EnterpriseAM reported, citing Al Bayan.

The latest cost figure for MGM Dubai is about AED 10bn

Published cost estimates for MGM Dubai, AED billions, 2026

MGM Resorts CEO, March: “more than $2 billion”
AED 7.3bn+
Wasl Group CEO, November: “about AED 10bn”
AED 10bn
Source: Gulf News; EnterpriseAM citing Al Bayan. US$ converted at the fixed rate of AED 3.6725 (Knock-On calculation). The two figures may not cover the same scope.

Why it matters

A resort of this size changes plans well beyond its own site. Hotel groups along Jumeirah and Umm Suqeim now know when 1,500 rooms of new competition arrive. Food, beverage and entertainment suppliers have a firmer date for contracts. And the slower timetable fits a wider pattern: EnterpriseAM reported that Dubai’s Construction Cost Index rose 11.64% year on year in July, according to Cavendish Maxwell, cement prices rose 16% between January and the end of August, and contractors are refusing fixed-price contracts on long projects. Construction contract awards fell 67% year on year in the third quarter to just under US$5bn (about AED 18.4bn, Knock-On calculation).

Building costs are up while new contract awards have dropped

Change in Dubai and UAE construction indicators, %, 2026

Dubai Construction Cost Index, year to July
+11.64%
Cement price, January to end-August
+16%
Construction contract awards, Q3 year on year
−67%
Source: EnterpriseAM, citing Cavendish Maxwell via Zawya. Bar lengths show the size of each change.

The knock-on effects

First order: a later date for contracts and hiring

Fit-out firms, furniture and equipment suppliers and restaurant operators linked to MGM Dubai must move delivery and revenue plans into 2029. A single-phase opening means demand for staff will come in one wave, so recruiters and training providers face a concentrated hiring push, likely in 2028, rather than a gradual one.

Second order: breathing room for nearby hotels

Beachfront hotels and restaurants in Jumeirah and Umm Suqeim get more time before 1,500 keys and 40 dining venues compete for the same guests. That matters at a time when hotel performance has softened; Emaar’s hotel occupancy fell to 63% in its nine-month results.

Third order: cost pressure spreads to other projects

If contractors keep avoiding fixed-price deals, developers will carry more cost risk on hotels, towers and branded homes. Buyers of off-plan projects such as the new Abu Dhabi branded residences may see longer handover times and more cautious launch pricing.

Who could benefit

  • Existing Jumeirah hotels: more time before a large new competitor opens.
  • Cement and materials suppliers: firmer prices while big projects keep building.
  • Recruitment and hospitality training firms: a large, single hiring wave ahead of 2029.

Who may face pressure

  • Suppliers and tenants tied to the old date: revenue moves further out.
  • Contractors on fixed-price deals: rising material costs squeeze margins.
  • Developers planning new towers: fewer contract awards and higher tender prices.

What to watch

  • Further announcements from Wasl and MGM, which Wasl’s chief executive said will come “in due course”.
  • The next Dubai Construction Cost Index readings from Cavendish Maxwell, for signs that cost growth is easing.
  • Transport links to Dubai’s coastal resorts, including the Dubai air taxi network.
  • More coverage: Knock-On UAE Property.

Sources

This is analysis, not investment advice. Figures are as of 19 November 2026.

Share this story

On your phone, tap Share to Story and choose Instagram or Facebook to post this story to your Story. Copy link copies the article address; on some devices it opens your share menu, where you tap Copy.

Spotted an error? Email corrections@knockonbrief.com with the article link. Have a tip? Write to tips@knockonbrief.com. See our Corrections Policy.

Leave a Reply

More from Knock-On

Discover more from Knock-On

Subscribe now to keep reading and get access to the full archive.

Continue reading